Which of the following events would result in a baseline update?
Correct Answer: B
Explanation/Reference: Explanation: 5.6.3.3 Project Management Plan Updates Project management plan updates may include, but are not limited to: * Scope Baseline Updates. If the approved change requests have an effect on the project scope, then the scope statement, the WBS, and the WBS dictionary are revised and reissued to reflect the approved changes through Perform Integrated Change Control process. * Other Baseline Updates. If the approved change requests have an effect on the project besides the project scope, then the corresponding cost baseline and schedule baselines are revised and reissued to reflect the approved changes.