In which Project Management Process Group is the project charter developed?
Correct Answer: C
Explanation/Reference: Explanation: Initiating Process Group. Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase. Process: 4.1. Develop Project Charter Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project. Inputs 1. Project statement of work 2. Business case 3. Agreements 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Expert judgment 2. Facilitation techniques Outputs 1. Project charter