Scope, schedule, and cost parameters are integrated in the:
Correct Answer: A
Explanation/Reference: Explanation: Performance Measurement Baseline (PMB). An approved, integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance. The PMB includes contingency reserve, but excludes management reserve.