Which of the following is an input to Control Scope?
Correct Answer: D
Explanation/Reference: Explanation: Process: 5.6 Control Scope Definition: The process of monitoring the status of the project and product scope and managing changes to the scope baseline. Key Benefit: The key benefit of this process is that it allows the scope baseline to be maintained throughout the project. Inputs 1. Project management plan 2. Requirements documentation 3. Requirements traceability matrix 4. Work performance data 5. Organizational process assets Tools & Techniques 1. Variance analysis Outputs 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates