Which is one of the major outputs of Sequence Activities?
Correct Answer: C
Explanation/Reference: Explanation: 6.3.3.1 Project Schedule Network Diagrams A project schedule network diagram is a graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities. Figure 6-11 illustrates a project schedule network diagram. A project schedule network diagram is produced manually or by using project management software. It can include full project details, or have one or more summary activities. A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. Any unusual activity sequences within the network should be fully described within the narrative. Process: 6.3 Sequence Activities Definition: The process of identifying and documenting relationships among the project activities. Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints. Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Milestone list 5. Project scope statement 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Precedence diagramming method (PDM) 2. Dependency determination 3. Leads and lags Outputs 1. Project schedule network diagrams 2. Project documents updates