A consultant is working on a Service Cloud implementation with a fixed budget and timeline. Additional requirements were discovered early on that will result in the project exceeding timeline and budget constraints. What is the first step the consultant should take to address the issue?
Correct Answer: B
When additional requirements are discovered that impact the project's timeline and budget, preparing a change order to account for these requirements is the first step. This involves adjusting the project scope, timeline, and budget to accommodate the new requirements, ensuring that all stakeholders are aligned and informed about the changes and implications for the project's delivery.