One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
Correct Answer: D
In this scenario, the program manager is using the "Exploit" risk response strategy, which is aimed at ensuring that an opportunity is realized. By transferring all resources to the project and arranging for overtime pay, the program manager is taking proactive steps to ensure the project is completed early, thereby securing the large bonus. According to PMI, the "Exploit" strategy is used when the objective is to ensure that the opportunity is realized, typically involving actions that maximize the chances of achieving the desired outcome.