A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago. What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?
Correct Answer: A
The SWOT analysis provides a broad overview of the project's strengths, weaknesses, opportunities, and threats. The next step for the interim risk manager is to break down these items into specific risks, categorized as threats (negative risks) or opportunities (positive risks). This classification allows for targeted risk response planning and aligns with PMI's risk management processes, which advocate for a clear identification and categorization of risks to derive actionable responses.