A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite. What should the risk manager advise the project team to do?
Correct Answer: B
When managing risks in a project that spans multiple regions with varying degrees of risk appetite, it is essential to align the project's risk thresholds with the organization's overall risk appetite. This approach ensures consistency across all regions and projects, particularly in multinational organizations where varying regional practices and risk appetites could create discrepancies. By aligning with the organizational risk appetite, the project team ensures that the risk management process adheres to the strategic objectives and governance framework set by the organization. This alignment also helps in managing stakeholder expectations and ensuring that the project remains within acceptable risk parameters set by the organization as a whole, as emphasized in the Risk Management Policy.