Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether. What should the risk manager do in this situation?
Correct Answer: C
In risk management, it is common that not all risks can be completely eliminated. Residual risk is the remaining risk after all possible mitigation efforts have been applied. If the residual risk iswithin the organization's risk appetite-meaning the organization is willing to accept this level of risk-it is appropriate to proceed with the plan. The PMI framework supports this approach, as risk management is about balancing effort and benefit, ensuring that mitigation efforts are commensurate with the risk involved.