Question 16/108

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described.
What is critical for the risk manager to consider when describing the causes?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (108q)
Question 1: A project manager managing a high-risk rating project was ju...
Question 2: During the project's lifecycle, project risk managers must m...
Question 3: A new company initiates a project to incorporate a cybersecu...
Question 4: A risk manager is reviewing documentation for a project foll...
Question 5: A risk manager has been assigned to a project in a company t...
Question 6: A company in the mining industry accommodates a lot of innov...
Question 7: A risk manager administered a pre-workshop risk survey in pr...
Question 8: Stakeholder deliverable reviews will start soon and addition...
Question 9: A project manager is developing the risk register and works ...
Question 10: When selecting strategies as an activity of Plan Risk Respon...
Question 11: A risk manager is facilitating a risk identification worksho...
Question 12: A company is preparing a formal response to bid for an infra...
Question 13: A project manager realizes the team undertaking the project ...
Question 14: A project manager is assigned to a new project and is told t...
Question 15: Some issues and unexpected results were found after completi...
Question 16: A risk manager documents the causes in the risk register and...
Question 17: A project team has completed the risk response plan for a ne...
Question 18: A new risk manager has been assigned to a project experienci...
Question 19: After presenting a list of risks to the major project stakeh...
Question 20: A risk manager and project team are managing a software syst...
Question 21: A project team has completed plan risk response activities a...
Question 22: A risk manager has a well-structured risk management process...
Question 23: An IT project is 40% complete. During the initial analysis, ...
Question 24: A risk manager has been assigned to an upcoming project. A s...
Question 25: A risk manager has been assigned to a project constructing a...
Question 26: The risk manager is facilitating risk planning activities wi...
Question 27: The project manager for project X was expecting the mobiliza...
Question 28: A software development project team was preparing for a phas...
Question 29: The project risk manager is in the process of identifying ri...
Question 30: A risk manager recently had to take an unexpected leave of a...
Question 31: A project is at the final development stage. The test lead i...
Question 32: A project has a significant impact on an organization. Multi...
Question 33: A web page for weather reports will be online next quarter. ...
Question 34: A project team in a multinational organization is working on...
Question 35: A company has implemented a policy requirement for employees...
Question 36: A risk manager has to inform a project sponsor of the expect...
Question 37: An organization that spans across different countries underg...
Question 38: A project manager has determined that an activity is too com...
Question 39: A project manager is working on a complex construction proje...
Question 40: A risk manager is preparing risk reports to be included in t...
Question 41: While executing an oil extraction project in an environmenta...
Question 42: After starting a new pipeline project, a risk manager schedu...
Question 43: A newly assigned risk manager realizes that a project has un...
Question 44: A risk manager reviews a Monte Carlo schedule risk analysis ...
Question 45: An agriculture government agency faces different challenges ...
Question 46: The project risk manager on a large firm fixed priced (FFP) ...
Question 47: A project is In the initiation phase. The project stakeholde...
Question 48: There is a debate within the organization on whether project...
Question 49: An organization faces immense competition in the market and ...
Question 50: In a complex project, individual risks have been identified ...
Question 51: A project is in the execution phase and involves large volum...
Question 52: A project team's manager is responsible for delivering a spe...
Question 53: A project team has just initiated a large project to move an...
Question 54: A financial institution is creating a new product database t...
Question 55: An organization with a portfolio of unique business function...
Question 56: As per the risk analysis process carried out for a project, ...
Question 57: A budget change request was initiated by a functional manage...
Question 58: The project manager is reviewing the lessons learned from a ...
Question 59: During a risk reassessment workshop with the project team an...
Question 60: A risk manager for a hospital extension project is leading a...
Question 61: A risk manager monitors risks on a medium-sized project by c...
Question 62: What should the risk owner use as an effective information-g...
Question 63: In a large industrial business, an on-going system developme...
Question 64: A project has consistently been lagging in cost performance ...
Question 65: The project risk manager for an environmental preservation p...
Question 66: A project is evaluating a new software to streamline the cur...
Question 67: in a complex and critical project, a sponsor asks the risk m...
Question 68: A subcontractor working on a project may cause delays in the...
Question 69: Three months into a program, multiple workstreams are showin...
Question 70: During a brainstorming session, a stakeholder identifies a r...
Question 71: Some project risks are applicable for the project's lifecycl...
Question 72: A project manager works on a long-term and high visibility p...
Question 73: A risk manager for a large project has completed documenting...
Question 74: The project sponsor asks the project manager about the accur...
Question 75: In a project to promote public health and mitigate health ri...
Question 76: A risk manager has been assigned to replace a risk manager o...
Question 77: An organization with a large computer network identified a p...
Question 78: A project manager wants to introduce a new technology to imp...
Question 79: The scope of a large mobile network deployment project inclu...
Question 80: A risk manager for a financial organization is assigned to s...
Question 81: A home solar panel project has many internal and external st...
Question 82: A risk manager faces resistance as they try to implement the...
Question 83: An organization is embarking on a multi-million-dollar proje...
Question 84: A risk manager for a cross-functional project is initiating ...
Question 85: During a virtual workshop presenting a product to potential ...
Question 86: During a meeting with a project team, a project manager asks...
Question 87: A company has a project whose objective is to extract gold r...
Question 88: A risk manager is managing risks of a mission critical appli...
Question 89: A project team identified some risks in a project. Team memb...
Question 90: The project team is updating the risk register with the mini...
Question 91: The project manager and the risk manager of a new project to...
Question 92: A key project is delayed and all contingency reserves have b...
Question 93: . A project manager is identifying risks on a project and de...
Question 94: A project manager has requested the risk manager's support i...
Question 95: The risk manager notices that in their workshops, most of th...
Question 96: As a project approached completion, a risk manager conducted...
Question 97: The stakeholders of a building construction project are not ...
Question 98: During a project progress meeting, a project team member is ...
Question 99: An organization performs an annual strategies and initiative...
Question 100: it typically takes 5 hours to perform a complete home inspec...
Question 101: A project team has completed the risk identification steps i...
Question 102: A list of risks was identified that could occur during the d...
Question 103: A project team does not understand why a very low probabilit...
Question 104: One project in a program needs to be completed in 6 months b...
Question 105: A risk management professional is currently facilitating the...
Question 106: A risk management team has completed a quantitative analysis...
Question 107: What is an example of legal and regulatory requirements and/...
Question 108: During the construction of a housing development, a project ...