During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?
Correct Answer: D
Sensitivity analysis is a quantitative risk analysis technique used to determine how variations in individual project risks affect project objectives, such as cost, schedule, or performance. Byanalyzing the sensitivity of these variables, the project team can identify which risks have the most significant potential impact on the project. This information is crucial for prioritizing risk responses and allocating resources effectively. PMI Risk Management Study Guide References: The PMI-RMP Exam Content Outline includes sensitivity analysis as a key technique in performing quantitative risk analysis, aiding in the identification of high-impact risks that require focused attention.