A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project. How should the risk manager address this concern?
Correct Answer: A
When a team member is struggling to ensure the coverage of all risks in a complex project, the risk manager should develop a risk breakdown structure (RBS). An RBS helps in systematically identifying risks by categorizing them into different levels and areas, making it easier to ensure that all potential risks are considered. This structured approach is particularly useful in complex projects where risks may arise from multiple sources. PMI advocates the use of an RBS as a best practice for comprehensive risk identification, particularly in large or complex projects where the range of potential risks can be extensive.