A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release. What should the risk manager have done to prevent this situation?
Correct Answer: B
Stakeholder engagement is critical in risk management, especially when decisions may impact project deliverables. By involving stakeholders more in risk management activities and decision-making processes, the risk manager could have ensured that all parties were aware of potential changes and their implications. This engagement helps in securing stakeholder buy-inand support, thus preventing situations where stakeholders might oppose decisions after the fact. PMI's risk management framework emphasizes the importance of continuous and active stakeholder engagement throughout the project lifecycle.