A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer's requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this. What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?
Correct Answer: D
Comprehensive and Detailed In-Depth Explanation: Extreme Programming (XP) emphasizescontinuous feedback, early testing, and adaptive planning. When discrepancies arise, XP encouragesidentifying root causes and taking corrective actionswithout delaying value delivery. Option D: Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery (Correct Answer). * Aspikeis a time-boxed research activity used toexplore a problem, test assumptions, and mitigate uncertaintyin XP methodology. * By running a spike, the teamanalyzes what went wrongin implementation and applies the findings to ensurefuture iterations align with customer needs. * The PMI-RMP Guide states that "proactive risk response planning helps teams course-correct and maintain delivery momentum" (PMI-RMP Exam Prep Study Guide, 2021, p.142). * TheAgile Practice Guidesupports the use of spikes, highlighting that "spikes allow agile teams to validate uncertainties in requirements, leading to more informed decision-making" (PMI & Agile Alliance, 2017, p. 89). Option A: Release this version and leave changes to be done at the end of the project phase (Incorrect). * XP emphasizescontinuous improvementandearly defect resolutionrather than postponing fixes. * Leaving changes until latermay increase technical debtand reduce user satisfaction. Option B: Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery (Partially Correct but Not the Best Answer). * While workshops help gather feedback, they do not providetechnical validationof what went wrong. * Aspike (Option D)is a better approach because it directly investigates the issue and leads to actionable changes. Option C: Ask the development team to brainstorm and come up with suggestions that will improve the delivery date (Incorrect). * Brainstorming maygenerate ideasbut does notanalyze the root causeof the discrepancies. * Without a structured approach like aspike, there is a risk of guessing rather than using data-driven solutions. Final Verdict:The best answer isD (Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery)because aspike provides empirical insights, leading to more effective corrective actions. References: * PMI.Agile Practice Guide(2017). PMI & Agile Alliance. * PMI.PMI-RMP Exam Prep Study Guide(2021).