Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges. What should the risk owner do?
Correct Answer: D
According to the PMBOK Guide, one of the tools and techniques for the implement risk responses process is root cause analysis. Root cause analysis is a technique that focuses on identifying the fundamental reason for the occurrence of a problem or a risk. By conducting a root cause analysis, the risk owner can determine why the implemented measures were only partially successful and what caused the new unforeseen risk to emerge. This can help the risk owner to identify and implement more effective risk responses, as well as to update the risk register and the risk report with the new information1 . References: PMBOK Guide, 6th edition,pages 452-453, 474-4751; PMI-RMP Exam Content Outline, 2015, page 8.