A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed. Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
Correct Answer: A
When a project experiences consistent deviations in cost performance index (CPI) and schedule performance index (SPI), it indicates underlying issues with the project's assumptions regarding schedule and resources. Analyzing these assumptions helps identify discrepancies between planned and actual performance, such as underestimated task durations or insufficient resource allocation. By revisiting and adjusting these assumptions, the risk manager can develop strategies to mitigate further overruns and align the project with its objectives. PMI Risk Management Study Guide References: The PMI-RMP Exam Content Outline emphasizes the importance of examining assumption and constraint analyses to identify risks arising from inaccurate or incomplete project assumptions, which can lead to performance issues.