Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
Correct Answer: A
After verifying the effectiveness of the risk responses, the next step is to close out the risk response actions and communicate the results to relevant stakeholders. This ensures that the project team and stakeholders are aware of how risks have been managed and that any lessons learned can be applied to future projects. This aligns with PMI's emphasis on communication and documentation in risk management to ensure transparency and continuous improvement.