Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available. What should the risk manager consider?
Correct Answer: D
According to the PMI-RMP Exam Content Outline1, one of the tasks in the domain of risk identification is to "review project documents, assumptions, and constraints, and understand the project environment and organizational factors to identify risks". The project charter, work breakdown structure (WBS), and scope statement are essential project documents that provide information about the project objectives, deliverables, requirements, assumptions, and constraints. Without these elements, the risk manager will have difficulty identifying and evaluating the risks that may affect the project. Therefore, the best answer is D. References: 1: PMI-RMP Exam Content Outline, page 7.