An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats. What should the risk manager do next?
Correct Answer: D
The risk manager should update the risk register with both the opportunities and threats identified during the SWOT analysis. This will help in tracking and managing all potential risks throughout the project lifecycle. Update the risk register with the identified risks Comprehensive and Detailed Explanation: According to the PMI Risk Management Professional (PMI-RMP)® Examination Content Outline1, one of the tasks in the domain of Risk Identification is to update the risk register with identified risks, causes, categories, and potential responses1. A risk register is a document used to track and report on project risks and opportunitiesthroughout the project's life cycle2. In this scenario, the risk manager should update the risk register with the identified risks, both opportunities and threats, that result from the SWOT analysis. The risk manager should also include the causes, categories, and potential responses for each risk, as well as other relevant information such as probability, impact, priority, owner, etc. The risk manager should not add only the threats to the risk register, because opportunities are also a type of risk that can havea positive effect on the project objectives and should be recorded andmanaged accordingly3. The risk manager should not utilize different tools to identify the risks, because the SWOT analysis is a valid and useful tool for risk identification and there is no indication that it was insufficient or inappropriate for the project context4. The risk manager shouldnot plan risk responses to the threats, because that is a separate process that comesafter risk identification and requires further analysis and evaluation of the risks5. References: 1: PMI Risk Management Professional (PMI-RMP)® Examination Content Outline, page 82: Risk Register in Project Management - Project Management Academy63: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, page 3974: How to Perform a SWOT Analysis - Project Risk Coach25: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Sixth Edition, page 440.