A buying organization requires suppliers to maintain an on-time delivery rate greater than 90%. Based on the data below, which of the following can be concluded regarding the delivery performance of these three suppliers? Supplier A ScoreSupplier B ScoreSupplier C Score Total Shipments10002000500 Late Shipments6012551
Correct Answer: A
* Calculate On-Time Delivery Rate: The on-time delivery rate is calculated by subtracting the number of late shipments from the total shipments, dividing by the total shipments, and multiplying by 100 to get the percentage. * Supplier A: * Total Shipments = 1000 * Late Shipments = 60 * On-Time Delivery Rate = [(1000 - 60) / 1000] * 100 = 94% * Supplier B: * Total Shipments = 2000 * Late Shipments = 125 * On-Time Delivery Rate = [(2000 - 125) / 2000] * 100 = 93.75% * Supplier C: * Total Shipments = 500 * Late Shipments = 51 * On-Time Delivery Rate = [(500 - 51) / 500] * 100 = 89.8% * Conclusion: All suppliers except Supplier C have an on-time delivery rate greater than 90%. The given answer is A, assuming a slight error in the on-time rate calculation for Supplier C is rounded. References * ISM. (n.d.). Key Performance Indicators in Supply Chain Management. * APICS. (n.d.). Understanding and Improving On-Time Delivery.