Valid PMI-PMOCP Dumps shared by ExamDiscuss.com for Helping Passing PMI-PMOCP Exam! ExamDiscuss.com now offer the newest PMI-PMOCP exam dumps, the ExamDiscuss.com PMI-PMOCP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-PMOCP dumps with Test Engine here:
The project sponsor and the manufacturing director of a PMO-managed project have different opinions about the development of a new order-tracking system. What should the PMO professional do to avoid this situation in the future?
Correct Answer: B
Conflicting opinions among key stakeholders typically arise whenstakeholders are not effectively engaged during requirements gathering and project planning. Involving all key stakeholders early (Option B) helps ensure comprehensive requirements, reduces misunderstandings, and fosters alignment. While scope and change control processes (Option A) are necessary, they do not replace stakeholder engagement. Roles matrices (Option C) and approvals (Option D) support governance but do not proactively prevent requirements misalignment. PMI-PMOCP Governance practices highlight early stakeholder involvement as a key success factor. References: PMI-PMOCPExam Content Outline, Governance Domain PMI Practice Standard for Project Management Offices (2013), Stakeholder Management PMI PMO Value Ring, Stakeholder Engagement