Valid PMI-PMOCP Dumps shared by ExamDiscuss.com for Helping Passing PMI-PMOCP Exam! ExamDiscuss.com now offer the newest PMI-PMOCP exam dumps, the ExamDiscuss.com PMI-PMOCP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-PMOCP dumps with Test Engine here:
A PMO professional at a software company is in charge of ensuring effective use of methodology and integration between projects, monitoring progress, and identifying any deviations from the defined objectives. Which responsibility describes the role of the PMO professional in this scenario?
Correct Answer: C
A key responsibility of a PMO professional is tomonitor project interdependencies and address issues that may impact project and portfolio outcomes. This oversight ensures coordinated execution and risk mitigation. Updating plans (Option A) and resource identification (Option D) are important tasks but more tactical. Analyzing test durations (Option B) is a project-level activity and less integrative. PMI-PMOCP Lifecycle Management highlights the PMO's role in integration and oversight for effective delivery. References: PMI-PMOCPExam Content Outline, Lifecycle Management Domain PMI Practice Standard for Project Management Offices (2013), Integration and Monitoring PMI PMO Value Ring, Portfolio Coordination