Valid PMI-PMOCP Dumps shared by ExamDiscuss.com for Helping Passing PMI-PMOCP Exam! ExamDiscuss.com now offer the newest PMI-PMOCP exam dumps, the ExamDiscuss.com PMI-PMOCP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-PMOCP dumps with Test Engine here:
In recent months, a company was contracted to deliver several projects requiring specialist technical resources. Several clients have begun to complain about the limited availability of the specialist technical resources, which will impact their project timelines. What should the PMO professional do to help solve the problem?
Correct Answer: B
Centralizing resource management (Option B) allows the organization tooptimize allocation of scarce specialist resources across projects, improving visibility, prioritization, and alignment with resource availability. Reviewing contracts (Option A) or asking PMs to hire additional resources (Option C) does not address systemic allocation issues. Supporting client relationships (Option D) is important but secondary. PMI-PMOCP Lifecycle Management highlights centralized resource coordination as essential in managing specialist resource constraints. References: PMI-PMOCPExam Content Outline, Lifecycle Management Domain PMI Practice Standard for Project Management Offices (2013), Resource Management PMI PMO Value Ring, Resource Optimization