Valid PSP Dumps shared by EduDump.com for Helping Passing PSP Exam! EduDump.com now offer the newest PSP exam dumps, the EduDump.com PSP exam questions have been updated and answers have been corrected get the newest EduDump.com PSP dumps with Test Engine here:
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
Correct Answer: D
Estimating Activity Durations: * The critical factors are crew size, labor hours, and the standard workday. * Cost estimation is not directly required to calculate durations. Evaluation of Options: * Option A: Incorrect. Crew size is needed for productivity estimation. * Option B: Incorrect. Labor hours are directly tied to durations. * Option C: Incorrect. Workday hours define the available time. * Option D: Correct. Cost is not directly linked to duration