When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
Correct Answer: D
Estimating Activity Durations: * The critical factors are crew size, labor hours, and the standard workday. * Cost estimation is not directly required to calculate durations. Evaluation of Options: * Option A: Incorrect. Crew size is needed for productivity estimation. * Option B: Incorrect. Labor hours are directly tied to durations. * Option C: Incorrect. Workday hours define the available time. * Option D: Correct. Cost is not directly linked to duration