Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
Correct Answer: A
Volume of Concrete per Column: * Each column requires 2,000 cubic feet of concrete. Lift Bucket Capacity: * Each lift bucket holds 40 cubic feet. Calculate Number of Lifts per Column: * Number of Lifts = Volume of Concrete ÷ Bucket Capacity = 2,000 ÷ 40 = 80 lifts. Cross-Verification: * Option B (50 lifts): Incorrect. Miscalculates required lifts. * Option C (5 lifts): Incorrect. Unrealistic for 2,000 cubic feet. * Option D (20 lifts): Incorrect. Underestimates. * Option A (80 lifts): Correct.