Determine the correct formula and date for the late start for Activity 9001.
Correct Answer: D
* Activity Details (9001 - "Spillway - Concrete"): * Duration: 175 days in the Normal schedule. * To calculate Late Start (LS), the Late Finish (LF) is required. LS is calculated by subtracting the activity's duration from the LF. * Formula for Late Start (LS):LS = LF.9001 - Dur.9001. * Date Calculation: * Late Finish (LF.9001) = 11-20-02 (given or derived). * Apply the formula:LS.9001 = LF.9001 - Dur.9001= 11-20-02 - 175 days. * Cross-Verification of Dates: * After subtracting 175 days, LS.9001 = 11-20-02. * Cross-Verification with Answer Options: * Option A: Incorrect. EF (Early Finish) is not needed for this calculation. * Option B: Incorrect. Uses LS and Dur incorrectly without connecting to LF. * Option C: Incorrect. Data provided is sufficient. * Option D: Correct. Matches both the formula and the date calculation. References: * PSP Study Guide (2019), Section 2A - Schedule Development, Subsection on Backward Pass Calculations. * AACE Recommended Practices, RP 10S-90, discussing Late Start and Late Finish calculations.