Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
Correct Answer: D
The change order impacts Activity 6001 by increasing its duration and workload. As per Critical Path Method (CPM) principles, this would also affect predecessor activities like 1000, which directly influence the start of 6001. Updates to the schedule will ripple through linked activities, but only those immediately affected by the change-1000 and 6001-would be revised in the immediate update. References: PSP Study Guide, Section 2.3.4 - Schedule Change Management, and Appendix A - Sample Problems on CPM Network adjustments highlight how scope changes propagate through linked activities.