If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
Correct Answer: B
When detailed estimates are unavailable, historical production rates can provide reliable data for estimating durations based on past projects with similar work. * Option A (Eichleay formula) is for overhead cost allocation. * Option C (Time impact analysis) evaluates delay impacts, not durations. * Option D (Black-Scholes model) is irrelevant in this context. Historical data usage is a recognized method in project planning and scheduling practices.