Valid PSP Dumps shared by ExamDiscuss.com for Helping Passing PSP Exam! ExamDiscuss.com now offer the newest PSP exam dumps, the ExamDiscuss.com PSP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PSP dumps with Test Engine here:
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
Correct Answer: B
Calculation of Total Lifts Required: * 3 column pours = 28×3=8428 \times 3 = 8428×3=84. * Additional lifts = 150150150. * Total lifts = 84+150=23484 + 150 = 23484+150=234. Lifts Per Day with One Crane: * 1 crane performs 30 lifts per day. Required Duration: * Minimum planned working duration = #234÷30#=18\lceil 234 \div 30 \rceil = 18#234÷30#=18. Verification with PSP Guidelines:Aligning workload with equipment capacity ensures practical schedule planning (Ref: PSP Study Guide, Chapter 2B: Workload Balancing).