If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
Correct Answer: C
Impact of Overrun: * Drafting (Activity C) and manufacturing (Activity D) are critical path activities. * A 5-day overrun in drafting consumes all available time for manufacturing. * Therefore, manufacturing cannot be delayed without affecting the release of the product. Verification with PSP Guidelines:The PSP Study Guide specifies that critical path activities have zero float, so delays propagate directly to the project finish (Ref: PSP Study Guide, Chapter 2A: Critical Path and Float).