SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
Correct Answer: C
A cost-benefit analysis for a subcontractor like SUBCO should focus on tangible and direct impacts to the project, including their labor and equipment rates, the potential for liquidated damages in the SDOT contract, and logistical concerns such as distance from the project site (PSP Study Guide, Section 1.2.4, "Project Variables"). Pending negotiations with a different entity, such as GOUGE, are unrelated to SUBCO's contract evaluation and are therefore not a consideration.