Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
Correct Answer: C
Schedule Update Procedures: * Accurate schedule updates rely on entering actual data (start/finish dates, durations) and evaluating impacts of changes. * "Downstream" logic revisions may be needed but are less critical compared to ensuring accurate historical data and reflecting immediate changes. PSP Study Guide References: * Schedule updating emphasizes capturing accurate historical data and estimating remaining durations accurately. Analysis of Options: * Option A and B: Key to progress tracking and forecasting. * Option D: Essential for reflecting impacts of delays and change orders. * Option C: While important, downstream logic revisions are less immediate compared to other procedures. Conclusion: The correct answer is C, as downstream logic revisions are less critical in achieving an accurate schedule forecast compared to other updates