<< Prev Question Next Question >>

Question 44/78

What is a key first step in developing a critical path method schedule?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (78q)
Question 1: Which of the following are NOT normally included in the proj...
Question 2: In order for a claimant to be entitled to an extension of co...
Question 3: Scenario: The entire network consists of the following activ...
Question 4: Determine the correct formula and date for the late start fo...
Question 5: These are the activities on the critical path: (Exhibit)...
Question 6: What day would Activity C complete if the duration of Activi...
Question 7: How many workdays occur from the start of the Product Testin...
Question 8: The activity with the most total float is: (Exhibit)...
Question 9: Which of the following documents is most likely to be of the...
Question 10: Assuming activities 2001 through 2004 comprise the same WBS ...
Question 11: Who will receive the most benefit from a master schedule of ...
Question 12: If Activity E's duration changes to 4 months, what is the ov...
Question 13: Which is NOT an industry-recognized methodology for quantify...
Question 14: If the administrative constraints for developing the precede...
Question 15: In analyzing a logical chain of activities in a critical pat...
Question 16: Which of the following will NOT affect the total float calcu...
Question 17: In a "crashed" schedule, which is a chain of activities that...
Question 18: What is the workweek period for this project? (Exhibit)...
Question 19: If after calculating a schedule an activity exhibits negativ...
Question 20: During proofing of the product manual, a problem was discove...
Question 21: Using the normal schedule and excluding general conditions, ...
Question 22: Which of the following is NOT required when performing weekl...
Question 23: Each of the following accurately describes total float in a ...
Question 24: Resource planning must take all of the following into accoun...
Question 25: Determine the driving activity for Activity 10001. (Exhibit)...
Question 26: If drafting of the product manual overruns its planned durat...
Question 27: Prior to the beginning work on Activity 6001, the scope is c...
Question 28: In the normal schedule, excluding Activity 1000. what activi...
Question 29: Determine the correct formula and date for the late finish f...
Question 30: Why does activity 11001 not show successor activities? (Exhi...
Question 31: Identify the minimum project duration. (Exhibit)...
Question 32: Considering the information provided for the project, what i...
Question 33: The characteristic of the precedence diagramming method that...
Question 34: A driving relationship is _____________________....
Question 35: What method offers the best chance of the schedule being use...
Question 36: Using the "normal" schedule, given Activity 3001 and the rel...
Question 37: When using a detailed estimate as the basis for work package...
Question 38: If no time extensions are granted and all actual delays are ...
Question 39: In the "normal" schedule, excluding Activity 1000, what acti...
Question 40: Assuming a total of 30 lifts per crane per day, what is the ...
Question 41: Activity C is a
Question 42: When reconstructing a CPM schedule electronically from a har...
Question 43: Assumptions made during the planning stage should be________...
Question 44: What is a key first step in developing a critical path metho...
Question 45: Which statement is true?
Question 46: Activity durations are normally estimated in an intuitive an...
Question 47: What is the free float for Activity F? (Exhibit)...
Question 48: The congested site only has room for 3 cranes to operate con...
Question 49: Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many ...
Question 50: Using the "crashed" schedule, if you start Activity 2002 on ...
Question 51: In its simplest form, what is the main drawback of critical ...
Question 52: Determine the correct formula and date for the late finish f...
Question 53: What is accurate about Activity 7001 in the precedence diagr...
Question 54: Which of the following is NOT required when initially planni...
Question 55: What method would be the best way to determine the most like...
Question 56: If a new hammock activity covering activities 6001 through 6...
Question 57: What problems can a soils engineer deal with on a project?...
Question 58: Which of these letters, symbols or words best approximates t...
Question 59: Under which circumstance should one perform resource-levelin...
Question 60: Determine the correct formula and date for the late finish f...
Question 61: Identify the late finish to develop plans and specs. (Exhibi...
Question 62: How many work days does it take to move the product from tes...
Question 63: Each column must be poured in one day. Each column requires ...
Question 64: Time-scaled logic diagrams are
Question 65: What is the remaining work duration of Active D? (Exhibit)...
Question 66: If a detailed estimate is NOT available to assist in the for...
Question 67: Which activity is drawn in the incorrect position? (Exhibit)...
Question 68: Which of the following types of delay will NOT result in a t...
Question 69: Of the following update procedures, which is the least impor...
Question 70: What does the heavy, vertical line at "X" represent? (Exhibi...
Question 71: Assuming that you had only one crane capable of 30 lifts per...
Question 72: What is the result of a forward pass calculation?...
Question 73: For which of these delays should an owner grant a time exten...
Question 74: In a graphical earned value analysis, what time-scaled value...
Question 75: Theoretically construct a summary activity for activities 20...
Question 76: What is the cycle time? (Exhibit)...
Question 77: Is activity 7001 pictured correctly in the precedence diagra...
Question 78: SUBCO is a potential concrete bridge contractor based in a m...