In its simplest form, what is the main drawback of critical path method scheduling?
Correct Answer: B
A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules. * Option A (backward pass) is a standard part of the CPM process. * Option C is incorrect as CPM considers activity dependencies. * Option D refers to flexibility in diagramming methods, not a drawback. The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.