Under which circumstance should one perform resource-leveling calculations?
Correct Answer: B
Resource-leveling is used when resource constraints such as labor, materials, or equipment availability might prevent schedule logic from being followed. * Option A references float-banking, unrelated to resource leveling. * Option C suggests never performing leveling unless required, which overlooks the need to address actual resource limitations. * Option D is incorrect as a resource-loaded schedule may still need leveling for optimization. Resource management principles in the PSP Study Guide discuss when and why to apply resource leveling.