If Activity E's duration changes to 4 months, what is the overall duration of the project.
Correct Answer: A
* Impact of Changing Activity E's Duration: * Activity E's new duration = 4 months. * The critical path passes through Activities A # C # D # E # H # I. * Recalculate Project Duration: * Original duration with E = 3 months: 19 months. * Increasing E to 4 months does not impact the overall path since it remains within the critical path's time allowance. * Overall project duration remains 19 months. * Cross-Verification: * Option B: Incorrect. Assumes additional delays. * Option C: Incorrect. Overestimates delays. * Option D: Incorrect. Miscalculates path changes. * Option A: Correct. Matches revised critical path duration. References: * PSP Study Guide (2019), Sections on Critical Path and Float Calculations. * AACE Recommended Practices, RP 10S-90.