Valid PSP Dumps shared by ExamDiscuss.com for Helping Passing PSP Exam! ExamDiscuss.com now offer the newest PSP exam dumps, the ExamDiscuss.com PSP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PSP dumps with Test Engine here:
If Activity E's duration changes to 4 months, what is the overall duration of the project.
Correct Answer: A
* Impact of Changing Activity E's Duration: * Activity E's new duration = 4 months. * The critical path passes through Activities A # C # D # E # H # I. * Recalculate Project Duration: * Original duration with E = 3 months: 19 months. * Increasing E to 4 months does not impact the overall path since it remains within the critical path's time allowance. * Overall project duration remains 19 months. * Cross-Verification: * Option B: Incorrect. Assumes additional delays. * Option C: Incorrect. Overestimates delays. * Option D: Incorrect. Miscalculates path changes. * Option A: Correct. Matches revised critical path duration. References: * PSP Study Guide (2019), Sections on Critical Path and Float Calculations. * AACE Recommended Practices, RP 10S-90.