Valid PSP Dumps shared by ExamDiscuss.com for Helping Passing PSP Exam! ExamDiscuss.com now offer the newest PSP exam dumps, the ExamDiscuss.com PSP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PSP dumps with Test Engine here:
In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?
Correct Answer: A
Time-Scaled Value for Reporting Intervals: * BCWS (Budgeted Cost of Work Scheduled) is plotted over time to represent the planned expenditure at specific intervals. * BCWS provides the basis for schedule and cost performance comparisons. Evaluation of Other Options: * B: BCWP is used to track actual progress. * C: SPI is a ratio, not a time-scaled value. * D: Actual cost of work scheduled is not a standard metric in earned value analysis. Verification with PSP Guidelines:The PSP Study Guide identifies BCWS as essential for time-scaled earned value analysis (Ref: PSP Study Guide, Chapter 1D: Earned Value Analysis).