In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?
Correct Answer: A
Time-Scaled Value for Reporting Intervals: * BCWS (Budgeted Cost of Work Scheduled) is plotted over time to represent the planned expenditure at specific intervals. * BCWS provides the basis for schedule and cost performance comparisons. Evaluation of Other Options: * B: BCWP is used to track actual progress. * C: SPI is a ratio, not a time-scaled value. * D: Actual cost of work scheduled is not a standard metric in earned value analysis. Verification with PSP Guidelines:The PSP Study Guide identifies BCWS as essential for time-scaled earned value analysis (Ref: PSP Study Guide, Chapter 1D: Earned Value Analysis).