Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Correct Answer: C
Activities not on the critical path are those with positive float, meaning they can be delayed without affecting the overall project completion time. The determination of such activities requires performing a forward and backward pass calculation as per CPM (Critical Path Method) analysis principles (PSP Study Guide, Section 2.2.4, "Relationships"). For example: * Identify the critical path by analyzing total float values (typically, critical path activities have zero total float). * Exclude activities that do not fall on the critical path.