For which of these delays should an owner grant a time extension?
Correct Answer: C
Granting Time Extensions: * Differing site conditions are excusable delays under standard contract terms, requiring time extensions. * Centrifuge delays and shop drawings typically fall under the contractor's responsibility and are not excusable. Excluded Options: * A & B: Shop drawing-related delays are the contractor's risk unless explicitly agreed otherwise. * D: Combining excusable and non-excusable delays does not entitle an extension. Verification with PSP Guidelines:Granting time extensions aligns with contractual principles outlined in PSP-related contracts (Ref: PSP Study Guide, Chapter 1C: Delay Analysis and Claims).