During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations. What should the project manager have done to avoid this?
Correct Answer: C
The project manager should ensure that all acceptance criteria are met for the user stories worked on in the iteration. This involves verifying that the features developed align with the quality standards required by regulations. Acceptance criteria are conditions that a software product must satisfy to be accepted by a user, customer, or other stakeholders12. By reviewing these criteria with the product owner, the project manager can ensure that the product meets the necessary quality standards before it is demonstrated to stakeholders, thus avoiding rejection during the system demo3. References: PMI's Code of Ethics and Professional Conduct, which outlines the responsibility of adhering to quality standards and regulations3. The PMBOK Guide, which provides guidelines for quality management and stakeholder engagement2. The PMI Guide to Business Analysis, which includes standards for business analysis and requirements management4.