A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing. What should the project lead do?
Correct Answer: D
In an agile project, the sprint review is the appropriate meeting for stakeholders, including board members, to attend. It is a formal opportunity to inspect the increment of the project's deliverables and adapt the product backlog if needed. The sprint review is designed to gather actionable feedback and foster collaboration between the development team and stakeholders12. : = Agile practices in project management encourage stakeholder involvement in product backlog and project progress1. The PMI also highlights the importance of stakeholder engagement in agile projects, suggesting their participation in planning and review sessions2. Additionally, the importance of board member attendance in meetings is emphasized as it is essential for legal transaction of business and effective board engagement3.