A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project. What should the project manager do?
Correct Answer: B
In a project where different teams are using different approaches (predictive and agile), it's important to respect the methodologies that each team is comfortable with. Forcing a single approach could disrupt the workflow and productivity of the teams. Instead, allowing the teams to continue with their chosen approaches while gradually adapting to a hybrid model can provide a balance. This approach respects the existing workflows while moving towards a more unified project management approach. The hybrid model combines the strengths of both predictive and agile approaches, providing flexibility and adaptability while maintaining a level of predictability. References: PMBOKGuide - Sixth Edition and Agile Practice Guide (Page 27, 3.1.3 Tailoring Considerations for Knowledge Areas)