A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available time to support the project, but was not planned to be involved in the current agile iteration. What should the project manager do?
Correct Answer: B
In an agile project environment, collaboration and flexibility are key. When an SME external to the project team offers a suggestion that could expedite project delivery, it is beneficial to leverage their expertise. The project manager should facilitate collaboration between the current team members and the SME to integrate the suggestion effectively. This approach aligns with agile principles, which prioritize individuals and interactions over processes and tools, and responding to change over following a plan12. References: Agile Methodology in Project Management as a Licensed PMP2. 5 Lessons on How Agile can Solve SME's Engagement Issues1.