A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?
Correct Answer: D
The Work Breakdown Structure (WBS) is a key project deliverable that organizes the team's work into manageable sections. The Project Manager can review the WBS to clarify the responsibilities of the data integration team and the data migration team. This can help to resolve any areas of overlap and ensure clear accountability for all project tasks. References: PMBOK Guide, 6th Edition, Section 5.4: Create WBS.