Correct Answer: A
Explanation
= The project manager should use a servant leadership style to accomplish this task. A servant leader is someone who focuses on serving the needs and interests of the team, rather than directing or controlling them.
A servant leader empowers the team to make decisions, fosters collaboration and trust, and supports the team's growth and development. A servant leader can help the team define the steps and identify the risks of migrating data to a new system by facilitating discussions, providing guidance, removing impediments, and ensuring alignment with the project vision and goals. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter
3: Project Management and Delivery Principles, Section 3.2: Leadership
Agile Practice Guide, Chapter 2: An Agile Mindset, Section 2.2: Empowerment and Collaboration
[PMP Exam Content Outline], Domain III: People, Task 7: Lead a team.