一個敏捷專案於 6 個月前啟動。自專案開始以來,由於部分團隊成員無法同時出席,團隊成員之間對於日常會議一直存在分歧。專案經理堅信敏捷團隊應該是自組織的,會議時間應該由團隊制定。
專案經理該做什麼?
Correct Answer: D
Explanation
According to the PMBOK Guide 7th Edition, the project manager should facilitate the creation of a team charter that defines the team's vision, values, norms, and working agreements. The team charter helps the team to align on the project purpose, goals, and expectations, and to resolve any conflicts or issues that may arise during the project. Therefore, the project manager should establish a team charter with the team members to agree on the daily meeting times and other aspects of the team collaboration. Option A is incorrect because it implies that the project manager is imposing a rigid schedule on the team, which goes against the agile principles of flexibility and adaptation. Option B is incorrect because it suggests that the project manager is delegating the responsibility of resolving the team conflicts to a team leader, which could undermine the team's self-organization and empowerment. Option C is incorrect because it indicates that the project manager is ignoring the team's disagreements and focusing only on their achievements, which could lead to unresolved issues and dissatisfaction. References: PMBOK Guide 7th Edition, Chapter 2: Creating a High-Performing Team, Section 2.1: Establishing a Team, p. 29-30.