專案團隊正處於產品遷移專案的規劃階段。專案經理安排與專案團隊、電信團隊以及負責集團產品帳務的部門領導舉行會議。會議的目的是根據需要轉移到新系統或在新系統中創建的內容量以及處理程序和時間範圍來確定專案時間表。
專案經理還應該邀請誰來參加會議?
Correct Answer: A
Explanation
= The service desk team is responsible for providing technical support and assistance to the end-users of the product. They are also involved in the testing and deployment of the product. Therefore, they should be invited to the meeting to provide their input and feedback on the product migration project. They can also help identify any potential issues or risks that may affect the product performance or user satisfaction. The provisioning team, the network team, and the reimbursement team are not directly related to the product migration project and may not have any significant contribution to the meeting. References: PMBOK Guide, PMP Question Bank PMBOK Guide, 7th edition, pages 54-55, 62-63 :