Correct Answer: B
Explanation
According to the PMBOK Guide 7th Edition, the project manager should engage stakeholders throughout the project life cycle and leverage their expertise, insights, and influence to achieve project objectives. In an agile approach, the project manager should also foster collaboration and communication among the project team and the stakeholders, and encourage feedback and adaptation. In this case, the project manager should recognize the stakeholder's skills as an asset for the project and evaluate the possibility of the stakeholder supporting the project team, either as a subject matter expert, a customer representative, a mentor, or a sponsor12. References: PMBOK Guide 7th Edition, Chapter 3: Project Performance Domain, Section 3.2:
Engage Stakeholders, Page 61; Chapter 5: Project Delivery Approaches and Life Cycles, Section 5.2: Agile Delivery Approach, Page 125.