Correct Answer: C
Explanation
According to the PMBOK Guide, 6th edition, a hybrid project is a project that uses a combination of predictive, iterative, incremental, and agile approaches to deliver the project objectives. A hybrid project may require different types of resources, skills, and methods to manage the project effectively. In this question, the project manager is leading a hybrid project that involves agile resources who are not at the same location as the project manager. The project also has a strict schedule and budget, which means that the project manager has to balance the scope, time, and cost constraints of the project. The question asks what the project manager should do in this situation.
Based on this information, the best answer is option C, which is to engage the agile resources through video conferencing on a daily basis. This is because video conferencing is a tool that can facilitate communication and collaboration among geographically dispersed team members. Video conferencing can also help the project manager to monitor the progress and performance of the agile resources, as well as to provide feedback and guidance. Video conferencing can also support the agile practices of daily stand-up meetings, sprint reviews, and retrospectives, which are essential for agile teams to deliver value and quality. Engaging the agile resources through video conferencing on a daily basis can help the project manager to overcome the challenges of leading a hybrid project, as well as to meet the schedule and budget constraints of the project.
Option A, which is to plan to have the agile resources temporarily relocate to the project manager's location, is not a good answer. This is because relocating the agile resources may not be feasible or cost-effective, as it may involve additional expenses, logistics, and risks. Relocating the agile resources may also disrupt their work environment, productivity, and motivation. Relocating the agile resources may not be necessary, as video conferencing can provide a similar level of interaction and collaboration.
Option B, which is to advise the sponsor that the project will be delayed as agile training will be required, is not a good answer. This is because delaying the project may not be acceptable, as the project has a strict schedule constraint. Delaying the project may also affect the stakeholder satisfaction, business value, and project benefits. Agile training may not be required, as the agile resources already have experience with agile.
The project manager may only need to provide some orientation and guidance on how the agile resources can work effectively with the rest of the project team.
Option D, which is to request a budget extension to get local resources experienced in agile, is not a good answer. This is because requesting a budget extension may not beapproved, as the project has a strict budget constraint. Requesting a budget extension may also indicate poor planning and resource management by the project manager. Getting local resources experienced in agile may not be easy or quick, as it may involve hiring, contracting, or training processes. Getting local resources experienced in agile may not be necessary, as the agile resources can work remotely with the project manager and the project team through video conferencing. References: PMBOK Guide, 6th edition, Chapter 1: Introduction1; Chapter 3: The Role of the Project Manager2; Chapter 9: Project Resource Management3; Chapter 10: Project Communications Management4; PMI, 2023, PMP Exam Content Outline, Domain II: Process, Task 7: Plan and manage project/phase resources.